FAR Part 11 clauses in the FAR overhaul: 18 codified clauses, 12 moved, removed or merged
Every clause the codified FAR places in FAR Part 11 (52.211), with the number under the deviation, the proposed number and the disposition. 12 not carried forward in the deviation text, 6 same number in the deviation text. As at 27 Sep 2026.
Codified in this part
18 clauses| Codified | Title | Under the deviation | Proposed | Disp. |
|---|---|---|---|---|
| 52.211-1 | Availability of Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29 | not carried forward | no proposed rule yet for this part | Rem. |
| 52.211-2 | Availability of Defense Specifications, Standards, and Data Item Descriptions in the Acquisition Streamlining and Standardization Information System (ASSIST) website | not carried forward | no proposed rule yet for this part | Rem. |
| 52.211-3 | Availability of Specifications Not Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions | not carried forward | no proposed rule yet for this part | Rem. |
| 52.211-4 | Availability for Examination of Specifications Not Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions | not carried forward | no proposed rule yet for this part | Rem. |
| 52.211-5 | Material Requirements | 52.211-5 | no proposed rule yet for this part | Kept |
| 52.211-6 | Brand name or equal | not carried forward | no proposed rule yet for this part | Rem. |
| 52.211-7 | Alternatives to Government-unique standards | not carried forward | no proposed rule yet for this part | Rem. |
| 52.211-8 | Time of Delivery | not carried forward | no proposed rule yet for this part | Rem. |
| 52.211-9 | Desired and Required Time of Delivery | not carried forward | no proposed rule yet for this part | Rem. |
| 52.211-10 | Commencement, Prosecution, and Completion of Work | not carried forward | no proposed rule yet for this part | Rem. |
| 52.211-11 | Liquidated Damages-Supplies, Services, or Research and Development | 52.211-11 | no proposed rule yet for this part | Kept |
| 52.211-12 | Liquidated Damages-Construction | 52.211-12 | no proposed rule yet for this part | Kept |
| 52.211-13 | Time Extensions | 52.211-13 | no proposed rule yet for this part | Kept |
| 52.211-14 | Notice of Priority Rating for National Defense, Emergency Preparedness, and Energy Program Use | 52.211-14 | no proposed rule yet for this part | Kept |
| 52.211-15 | Defense Priority and Allocation Requirements | 52.211-15 | no proposed rule yet for this part | Kept |
| 52.211-16 | Variation in Quantity | not carried forward | no proposed rule yet for this part | Rem. |
| 52.211-17 | Delivery of Excess Quantities | not carried forward | no proposed rule yet for this part | Rem. |
| 52.211-18 | Variation in Estimated Quantity | not carried forward | no proposed rule yet for this part | Rem. |
Which number a given contract carries depends on the deviation its awarding agency has adopted and the date of the solicitation or the modification: a contract carries the deviation number only where its agency adopted that deviation and it applies at that date. The finder shows all three numbers and names the source; it does not decide for you. Confirm which deviation your contracting officer's agency has adopted.